News
Work in Progress:
Pulling wire throughout for branch circuits.
Installing duct on 1st floor.
Complete domestic water rough-in on the 2nd floor.
Sanitary piping rough-in has been completed on the 3rd floor.
Completing remaining framing throughout.
Starting door frame…
Work in Progress:
Forming lift 3 on elevator #1.
Working on retaining wall progressing south to column line A7.
Pile caps and foundations for elevator #2 are complete.
Looking forward:
Pour lift #3 on elevator #1 on 4/8/2016.
Steel delivery and erection begins for…
鶹Ƶ’s fourth annual Neuroscience Symposium will cover the latest research findings on “The Neuroscience of The Social Brain” on April 7-8 at the 鶹Ƶ Hotel and Conference Center located in downtown Kent, Ohio.
Image
Theresa Benyo already had an exciting and fulfilling career as a project manager at NASA. With a great job, a house, a husband, two kids, and hobbies like musical theatre what more could you want? Academically speaking, she’d already earned a dual bachelor’s degree in physics…
Work in Progress:
Working on pile caps and grade beams. Plan to start column line 17 (Southern most column line) next week.
Started working on forming elevator #2 (South).
Pouring elevator #1 second lift (North) today.
Continuing the installation of the basement…
Work in Progress:
First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun.
Room 101 & 104 electrical rough-in is at 90% complete.
Machine Shop electric panel installed and completed on Saturday 3/19.
Room 223 electrical…
Work in Progress:
Steam piping in the 3rd floor east mechanical room is 20% complete.
Steam condensate lines for the steam station and AHU#1 are in progress.
Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…
Senior Research Fellow Quan Li, Ph.D., and his research group at 鶹Ƶ’s Liquid Crystal Institute®, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device…
Work in Progress:
Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18. Will be ready for cooling system startup on 4/15.
Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
Steam reducing station…
Work in Progress:
New restroom plumbing rough-in nearly complete.
Sheet metal duct rough-in has begun on the first floor and the new restroom areas.
Electrical floor boxes are 75% complete in 223.
Sanitary drain and toilet carriers are complete in the second floor.
3rd…