Â鶹ÊÓƵ

4/21- Smith Hall Renovation Updates

Work in Progress:

  • Currently installing 1J electric panel, wire and raceways. Confirmed an electric shutdown will not be required now.
  • Continuing to pull wire throughout.
  • Continuing with HVAC sheet metal duct work on the 1st and second floor.
  • Completing domestic water piping rough-in for drywall boarding.
  • Framing continues for stairwell partitions.
  • Steel erection is substantially complete.

Looking Forward:

  • Cut masonry opening for AHU penetrations in south wall.
  • In-fill window openings with masonry at AHU location on the second floor.
  • AHU Curb delivery scheduled for 4/27.
  • Remaining demolition and abatement of tile work schedule for week of 4/25.
  • 3rd floor HVAC work to start week of 4/25.
  • Drywall and taping throughout building.
POSTED: Thursday, April 21, 2016 06:09 PM
Updated: Saturday, December 3, 2022 01:02 AM