1/28- Williams & ISB Construction Updates

Work in progress:

  • Demolition of south stairs is complete including the foundations.
  • Test pile will be tested on 1/29/16.
  • Steam Condensate receiver in Williams Hall will take place on Saturday with UFM shutdown.
  • Auger Cast pile installation to begin next week and progress south to column line 6 by end of week.
  • Shoring is about 80% complete.  Working on east side.
  • Mass excavation continues on the South end.

Looking a week ahead:

  • Tie in sanitary service lines extending south of the site inside fenced area.
  • Pile caps and water proofing to start 2/8/16 .